Value: $3.7 Million

Overview

ABACM is currently undertaking a temporary charging solution to Tuggeranong Bus Depot (TBD) Via a new high voltage supply and High Voltage Switching Stations to enable a portable, ‘drop in’ charging solution (Charging Equipment) and containerised, portable, ‘drop in’ charging solution (Charging Equipment) for Battery Powered Electric Buses (BEBs) and associated infrastructure

Effectively redesigned electrical equipment to be incorporated within the existing landscape to avoid tree damaging activities. Developed and coordinated internal traffic management plans to mitigate disruptions and enable the Bus Depot to continue operations whilst the works are undertaken.

COMPLETED 2026