Dickson DPF Stormwater Harvesting Scheme
Value: $1.7 million
Overview
The project scope includes the installation three (3) by 400KL tanks, One (1) x 500KL Tanks including pump house to enable stormwater harvesting and connection to Dickson wetlands. ABACM also undertook the upgrades to the existing oval irrigation system.
ABACM successfully managed the completion of the reticulation and harvesting system. Quality assurance outcomes reducing the ongoing cost of water demands on Dickson district playing fields (DPF).
Completed 2011